Issue Date: May 7, 2014
Comment Deadline: June 6, 2014
Corps Action ID Number: SAW-2013-01285
The Wilmington District, Corps of Engineers (Corps) has received an application from Marty Gilbert of Walmart Stores Inc., seeking Department of the Army authorization to permanently impact 931 linear feet of jurisdictional stream channel, 0.08 acre of forested jurisdictional wetlands and 1.26 acres of open water (existing pond) of a tributary of Crooked Run Creek associated with the proposed construction of a new Walmart Supercenter located east of U.S. Highway 52 at the intersection of Ingram Drive and Five Forks Street, in King, Stokes County, North Carolina.
Specific plans and location information are described below and shown on the attached plans. This Public Notice and all attached plans are also available on the Wilmington District Web Site at http://www.saw.usace.army.mil/Missions/RegulatoryPermitProgram.aspx
Applicant:
Walmart Stores Inc.
Attn: Marty Gilbert
702 SW 8th Street
Bentonville, AR 72716-8611
Agent:
S&ME, Inc.
Attn: Darrin M. Peine
9751 Southern Pine Boulevard
Charlotte, NC 28273-5560
Authority
The Corps evaluates this application and decides whether to issue, conditionally issue, or deny the proposed work pursuant to applicable procedures of the following Statutory Authorities:
X - Section 404 of the Clean Water Act (33 U.S.C. 1344)
- Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403)
- Section 103 of the Marine Protection, Research and Sanctuaries Act of 1972 (33 U.S.C. 1413)
Location
Directions to Site: The project site is an existing pasture and stock pond located north of U.S. Highway 52 at the intersection of Ingram Drive and Five Forks Street, in King, Stokes County, North Carolina. Coordinates (in decimal degrees) for the site are 36.265206º North, -80.365736º West. The site is located in the Yadkin River Basin (8- Digit Cataloging Unit 03040101).
Project Area (acres): 39 Nearest Town: King
Nearest Waterway: Crooked Run Creek River Basin: Yadkin
Latitude and Longitude: 36.265206N, -80.365736W
Existing Site Conditions
The land use in the immediate area surrounding the project consists of existing commercial retail or townhouse residential. The project site itself is an existing active cow pasture and stock pond.
Applicant’s Stated Purpose
As stated by the applicant, the purpose of the project is to provide adequate and cost effective products to its customers within the King, North Carolina and surrounding community.
Project Description
The proposed project is to construct a new Walmart Supercenter building including public road access, supporting customer and employee parking, and necessary shipping and receiving truck dock facilities. The proposed Walmart Supercenter is planned to provide a 24 hour shopping experience for electronics, apparel, toys, home furnishings, and grocery store. Also include are specialty shops such as pharmacies, banks, hair salons, restaurants, and vision or health clinics.
Compensatory Mitigation
The applicant offered compensatory mitigation for the proposed 931 linear feet of stream channel impact and 0.08 acre of wetland impact at a 1:1 ratio. There are no private mitigation banks available within the 8-digit hydrologic unit code for this project. Therefore, the applicant has applied for mitigation credits from the North Carolina Ecosystem Enhancement Program (NCEEP). He included copy of the mitigation acceptance letter from the NCEEP dated April 8, 2014 with his application package.
Essential Fish Habitat
Pursuant to the Magnuson-Stevens Fishery Conservation and Management Act, this Public Notice initiates the Essential Fish Habitat (EFH) consultation requirements. The Corps’ initial determination is that the proposed project would not effect EFH or associated fisheries managed by the South Atlantic or Mid Atlantic Fishery Management Councils or the National Marine Fisheries Service.
Cultural Resources
Pursuant to Section 106 of the National Historic Preservation Act of 1966, Appendix C of
33 CFR Part 325, and the 2005 Revised Interim Guidance for Implementing Appendix C, the District Engineer consulted district files and records and the latest published version of the National Register of Historic Places and initially determines that:
- Should historic properties, or properties eligible for inclusion in the National Register, be present within the Corps’ permit area; the proposed activity requiring the DA permit (the undertaking) is a type of activity that will have no potential to cause an effect to an historic properties.
X - No historic properties, nor properties eligible for inclusion in the National Register, are present within the Corps’ permit area; therefore, there will be no historic properties affected. The Corps subsequently requests concurrence from the SHPO (or THPO).
- Properties ineligible for inclusion in the National Register are present within the Corps’ permit area; there will be no historic properties affected by the proposed work. The Corps subsequently requests concurrence from the SHPO (or THPO).
- Historic properties, or properties eligible for inclusion in the National Register, are present within the Corps’ permit area; however, the undertaking will have no adverse effect on these historic properties. The Corps subsequently requests concurrence from the SHPO (or THPO).
- Historic properties, or properties eligible for inclusion in the National Register, are present within the Corps’ permit area; moreover, the undertaking may have an adverse effect on these historic properties. The Corps subsequently initiates consultation with the SHPO (or THPO).
- The proposed work takes place in an area known to have the potential for the presence of prehistoric and historic cultural resources; however, the area has not been formally surveyed for the presence of cultural resources. No sites eligible for inclusion in the National Register of Historic Places are known to be present in the vicinity of the proposed work. Additional work may be necessary to identify and assess any historic or prehistoric resources that may be present.
The District Engineer’s final eligibility and effect determination will be based upon coordination with the SHPO and/or THPO, as appropriate and required, and with full consideration given to the proposed undertaking’s potential direct and indirect effects on historic properties within the Corps-indentified permit area.
Endangered Species
Pursuant to the Endangered Species Act of 1973, the Corps reviewed the project area, examined all information provided by the applicant and consulted the latest North Carolina Natural Heritage Database. Based on available information:
X - The Corps determines that the proposed project would not affect federally listed endangered or threatened species or their formally designated critical habitat.
- The Corps determines that the proposed project may affect federally listed endangered or threatened species or their formally designated critical habitat. The Corps initiates consultation under Section 7 of the ESA and will not make a permit decision until the consultation process is complete.
- The Corps is not aware of the presence of species listed as threatened or endangered or their critical habitat formally designated pursuant to the Endangered Species Act of 1973 (ESA) within the project area. The Corps will make a final determination on the effects of the proposed project upon additional review of the project and completion of any necessary biological assessment and/or consultation with the U.S. Fish and Wildlife Service and/or National Marine Fisheries Service.
Other Required Authorizations
The Corps forwards this notice and all applicable application materials to the appropriate
State agencies for review.
North Carolina Division of Water Resources (NCDWR):
The Corps will generally not make a final permit decision until the NCDWR issues, denies, or waives the state Certification as required by Section 401 of the Clean Water Act (PL 92-500). The receipt of the application and this public notice, combined with the appropriate application fee, at the NCDWR Central Office in Raleigh constitutes initial receipt of an application for a 401 Certification. A waiver will be deemed to occur if the NCDWR fails to act on this request for certification within sixty days of receipt of a complete application. Additional information regarding the 401 Certification may be reviewed at the NCDWR Central Office, 401 and Buffer Permitting Unit, 512 North Salisbury Street, Raleigh, North Carolina 27604-2260. All persons desiring to make comments regarding the application for a 401 Certification should do so, in writing, by June 6, 2014 to:
NCDWR Central Office
Attention: Ms. Karen Higgins, 401 and Buffer Permitting Unit
(USPS mailing address): 1650 Mail Service Center, Raleigh, NC 27699-1650
Or,
(physical address): 512 North Salisbury Street, Raleigh, North Carolina 27604
North Carolina Division of Coastal Management (NCDCM):
- The application did not include a certification that the proposed work complies with and would be conducted in a manner that is consistent with the approved North Carolina Coastal Zone Management Program. Pursuant to 33 CFR 325.2 (b)(2) the Corps cannot issue a Department of Army (DA) permit for the proposed work until the applicant submits such a certification to the Corps and the NCDCM, and the NCDCM notifies the Corps that it concurs with the applicant’s consistency certification. As the application did not include the consistency certification, the Corpswill request, upon receipt,, concurrence or objection from the NCDCM.
X - Based upon all available information, the Corps determines that this application for a Department of Army (DA) permit does not involve an activity which would affect the coastal zone, which is defined by the Coastal Zone Management (CZM) Act (16 U.S.C. § 1453).
Evaluation
The decision whether to issue a permit will be based on an evaluation of the probable impacts including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, flood plain values (in accordance with Executive Order 11988), land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and, in general, the needs and welfare of the people. For activities involving the discharge of dredged or fill materials in waters of the United States, the evaluation of the impact of the activity on the public interest will include application of the Environmental Protection Agency’s 404(b)(1) guidelines.
Commenting Information
The Corps of Engineers is soliciting comments from the public; Federal, State and local agencies and officials, including any consolidated State Viewpoint or written position of the Governor; Indian Tribes and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment (EA) and/or an Environmental Impact Statement (EIS) pursuant to the National Environmental Policy Act (NEPA). Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.
Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider the application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. Requests for a public hearing shall be granted, unless the District Engineer determines that the issues raised are insubstantial or there is otherwise no valid interest to be served by a hearing.
The Corps of Engineers, Wilmington District will receive written comments pertinent to the proposed work, as outlined above, until 5pm, June 6, 2014. Comments should be submitted to John Thomas, Regulatory Project Manager,Raleigh Regulatory Field Office, 3331 Heritage Trade Drive, Suite 105 ,Wake Forest, North Carolina 27587, at (919) 554-4884 ext 25.