MANTEO – (SHALLOWBAG) BAY, NORTH CAROLINA
Executive Summary
Introduction
The Manteo (Shallowbag)
Bay project is a product of extensive investigation, analysis and coordination
for over 30 years. In the process
of developing the plan, the Corps has addressed, in great detail, the views and
concerns of the other Federal agencies and interested parties and has properly
considered alternatives, environmental consequences and mitigation.
Following the Federal planning guidelines, Principles and Guidelines
(P&G), consideration of project impacts on fish and wildlife has been
central to the planning of this project and significant modifications are
proposed that are intended to diminish or eliminate the environmental impacts of
the project. The Corps believes the
proposed project avoids or appropriately mitigates for environmental damage that
might arise from its construction, while providing a safe and reliable channel
for navigation projects. The
project, as planned, satisfies Federal guidelines to develop a plan that
contributes to national economic development consistent with protecting the
Nation’s environment.
Existing Project
The purpose of the Manteo (Shallowbag) Bay project is to provide a safe, reliable navigable channel from the Atlantic Ocean through Oregon Inlet to Roanoke Sound and connecting channels to Pamlico Sound. The existing project provides:
Purpose and Need for Project Improvements.
The need for the proposed project arises from the fact that Oregon Inlet has heavy vessel traffic since it is the only navigable inlet between Cape Henry, Virginia, and Hatteras Inlet, North Carolina. Oregon Inlet is located about 45 miles north of Hatteras Inlet and 85 miles south of Cape Henry. A report projecting commercial fish landings through Oregon Inlet (Street 1997) indicated that vessels from many other North Carolina ports as well as other states use Oregon Inlet when conditions permit safe navigation. Vessels using the inlet represent both commercial and recreational fishing interests.
The Corps of Engineers has been attempting to maintain the 14-foot deep by 400-foot wide channel across the ocean bar at Oregon Inlet since 1962. Between 1962 and 1965, channel maintenance was accomplished with Corps of Engineers hopper dredges. Between 1965 and 1982 the channel was maintained primarily by Corps of Engineers sidecast dredges. During the early 90's, hopper dredge operations were limited to the months of December through March due to concerns over the safety of sea turtles. During that period, maintenance of the bar channel was accomplished with ocean certified pipeline dredges which deposited the dredged material on the north end of Pea Island between 1 and 2 miles south of Oregon Inlet.
Historical Review of Oregon Inlet -
Manteo (Shallowbag) Project
Recommended Plan
The proposed project provides for stabilization of Oregon Inlet with a dual rubble-mound jetty system. The north jetty length is 10,950 feet and includes a 1000-foot long weir section. The south jetty including the terminal groin is 6,575 feet long. After shoreline adjustment, the jetties would extend approximately 2500 feet into the ocean. The plan also includes a sand by-passing system for adjacent beaches, a channel 20’x400’ through the ocean bar, and a channel 14’x120’ from the gorge in Oregon Inlet to and through Roanoke Sound to and including a 15-acre boat basin of the same depth at Wanchese. A physical and biological monitoring plan will be developed to address long term implications of the project. The following table presents the real estate requirements for the project on DOI lands.
The average annual cost of the
project is estimated to be $4,520,000 and the estimated average annual benefits
are $7,237,000. This results in net
project benefits of $2,708,000 and a benefit-to-cost ratio of 1.6.
The total first cost of the project is $91,758,000 (October 1997 price
level). The current fully funded
total project cost is estimated to be $111,000,000.
The schedule for completion of the GDM and EIS is presented in the
following table.
Schedule for Completion of the GDM & EIS Supplements
Milestone Event Schedule
Complete
Revisions to Draft Supplement III
08-Jan-99
Submit Draft Supplements to Public & Agency
00-Jan-00
Public Review notice in Federal Register
00-Jan-00
Public and Agency Review Complete
00-Jan-00
Comment Responses, Draft Revisions Complete
03-Aug-01
Print Revised Supplements, Submit Final to SAD/HQ
06-Aug-01
HQ Approves Final Release
04-Sep-01
Notice of Final Supplement in Federal Register
21-Sep-01
Public & Agency Review
23-Oct-01
Final Comments to SAW
06-Nov-01
Prepare Draft ROD Package
30-Nov-01
Submit Draft ROD Package to ASA(CW)
07-Dec-01
Planning Process and NEPA Requirements
The Presidentially directed Planning Guidelines (Principles and Guidelines), used by the Corps, incorporate NEPA requirements into the planning and decision making process. The planning steps are logical and address 4 Accounts:
National Economic Development (NED)
Environmental Quality (EQ)
Regional Economic Development (RED)
Other Social Effects (OSE).
The 4 accounts are designed to capture ecological, cultural, and aesthetic resource considerations required by NEPA. These steps and system of accounts have been carefully and repeatedly followed for the Manteo (Shallowbag) Bay project. In fact, since 1970, this process, as depicted in the following table has been repeated numerous times.



The Federal objective for plan selection is to recommend the NED plan, which is the alternative “with the greatest net economic benefit consistent with protecting the Nation’s environment”. The proposed plan meets this criteria.
Alternatives evaluated in the 35+ years of planning and engineering on this project include:
Sand by-passing
Jetty positioning, length and spacing
Wiers
Breakwaters
The following table presents a comparison of the alternative solutions. Costs and benefits are shown as incremental changes between the with and without condition (continued maintenance of a 14’ channel)
|
Plan |
Average
Annual Costs |
Average
Annual Benefits |
Net
Benefits |
Benefit/Cost
Ratio |
|
Dredging Deeper Channel (20’) |
$8,148,400 |
$6,237,000 |
-$1,911,400 |
.8 |
|
Jetty Alternative |
$4,520,000 |
$7,237,000 |
$2,717,000 |
1.6 |
Documentation and Coordination
The existing project was authorized in 1950 and constructed beginning in 1960. Since then the following major reports have been prepared and coordinated:
1970 Feasibility Report for improved project (jetties and deeper channel)
1977 Final Phase I General Design Memorandum (GDM) and Environmental Impact Statement (EIS)
1980 Phase II General Design Memorandum and Final EIS Supplement I
1985 Final EIS Supplement II
1997 Feature Design Memorandum on Sand By-Passing
2001 Final GDM Supplement II and Final EIS Supplement III
The supplemental GDM’s and EIS’s were prepared to address modifications in the project to address economic reevaluations and agency concerns concerning larval transport and shoreline erosion.
Project Issues
The areas of controversy associated with the Manteo (Shallowbag) Bay, North Carolina, project are numerous and long-standing as evidenced by the four environmental impact documents which have been prepared for the project dating back to September 1977. The controversies can be distilled to four categories: concerns about the effects of the proposed jetties on the movement of larval organisms through Oregon Inlet; concerns about the effects of the jetties and sand bypassing system on natural littoral processes; concern about the adequacy and commitment to mitigation needs; and concern that the no action plan and dredging only plan have not been adequately evaluated. The Department of Interior has denied special use permits required for the proposed plan, citing incompatibility with management philosophy and guidelines for their lands.
These issues are long standing and have been addressed in each of the NEPA reports and further detailed in response to the referral from NOAA. The following presents the major actions taken by the Corps to address these concerns.
Corps Actions

GAO Audit
Senator Edwards, North Carolina and Senator Baucus, Montana, requested a GAO audit of the project. The audit is currently underway with the following objectives:
Is the Corps’ economic analysis of the project reasonable and useful for decision making?
Will the Corps still require dredging of the Inlet once the project is completed and, if so, how much and at what cost?
Did the Corps consider lessons learned from similar jetty projects in its decision maki9ng on the Oregon Inlet project?
At present, their findings are expected in the spring of 2002.
Project Support
The State of North Carolina, as the project sponsor, continues to show strong support for the project. Active support comes from the governor’s office and the North Carolina Department of Commerce. Congressman Walter Jones, Jr. and Senator Jesse Helms also continue to be active supporters of the project.